All projects
P07 / Course project · Wind farm planning · Group project2025

Planning a near-shore wind farm at Omø.

A feasibility study for a 216 MW near-shore wind farm south of Omø: wind resource assessment, layout and IEC site assessment in WAsP and WAT, energy yield with losses and uncertainties, grid connection and economics.

DTU · COURSE 46200Planning and Development of Wind Farms
WAsPWAsP Climate AnalystWAsP EngineeringWindfarm Assessment Tool (WAT)QGISIEC 61400-1LCOE & NPV
WAsP colour map of capacity factor around Langeland and Omø, with the 27 turbines of the final layout drawn as two curved rows in the water.
Resource grid from WAsP. The capacity factor ranges from about 37% over land (blue and green) to 50% over open water (red), with the final layout of 27 turbines in two curved rows.

Net energy yield, P90

623.8 GWh / year

After wake and technical losses of 11.6%. The P50 estimate was 788.4 GWh per year.

Best-case net present value

−176 M€

P50, 30-year life. All nine lifetime and confidence scenarios gave a negative NPV, so the project was judged not feasible.

The goal

An earlier offshore wind farm proposed near Omø, Omø Syd, was rejected because it lay inside a protected nature area. This course project planned a replacement: a new site south of Omø, a farm of 27 Vestas V164 8 MW turbines (216 MW), an estimate of its yearly energy production, and an assessment of whether it would pay off.

My involvement

Responsible for the site selection and environmental impact assessment, the wind resource assessment in WAsP, the layout, IEC site assessment and energy-yield calculations in WAsP and WAT, and the grid connection and foundation choice.

Choosing the site

Ship traffic, protected areas and nearby wind farms around Omø were mapped, and the farm was placed at two sites west of the main shipping lane (West 1 and West 2). They lie outside the protected areas and close to Nakskov harbour, which has a Vestas factory. Three alternative sites had better wind, but all of them lie inside protected areas.

Wind resource

The met mast had about three years of 10-minute data at 51 m. A winter gap ruled out two consecutive years, so two separate full years were used. More than 97% of the readings were valid in both years. WAsP Climate Analyst gave a generalised mean wind of 6.9 m/s at 10 m, mostly from the west. For the 50-year extreme wind, the spectral-correction method gave 24 ± 1.3 m/s at 10 m. The annual-maximum and peak-over-threshold methods agreed with this, but with much larger uncertainty, because two years give them too few samples.

Layout and site assessment

Three layouts with 27 turbines each were compared, with turbines spaced at least 6.1 rotor diameters apart:

LayoutDesignWake loss (WAsP)
AThree rows across both sites4.04%
CThree straight rows7.30%
DTwo curved rows5.49%

Wake losses calculated in WAsP for the three layouts, before any other losses.

Layout A had the lowest wake loss, but its turbines are split by the shipping lane, which means extra cables. Layout D was chosen: two curved rows inspired by Middelgrunden, which also has the least visual impact. In the IEC site assessment, class IB failed the wind speed distribution check, and the effective turbulence corrected with mast data also exceeded IB. The site therefore needs an S-class design, which the V164 already uses.

Energy yield

With layout D fixed, the analysis added technical losses (availability, transmission, degradation and electrical, about 7.5% in total) and an uncertainty budget of 15.7%. This combines wind-speed uncertainty (8.7%, mainly from only two years of data and the 51 m mast being far below the 105 m hub height) and other sources (7.9%). WAT then gave the yield at three confidence levels:

Confidence levelGross AEPNet AEP (all losses)Total loss
P50844.6 GWh788.4 GWh10.9%
P75790.6 GWh701.9 GWh11.2%
P90705.7 GWh623.8 GWh11.6%

Annual energy production of layout D calculated in WAT. P90 is the yield exceeded with 90% probability.

The farm would connect to the 132–150 kV grid, either at Svendborg (25.7 km of cable) or at Stigsnæsværket (29.4 km, along an existing approved cable corridor). The water is 14–20 m deep, so monopiles were recommended, with a gravity base as the fallback if the glacial seabed proves too costly to drive piles into.

Result

With these yields, the economic model gave a levelised cost of energy of 89–125 €/MWh, depending on lifetime and confidence level. The global offshore average in 2023 was about 78 €/MWh. With a contract-for-difference strike price based on the Vesterhav auction, the net present value was negative in every scenario, so the farm was judged not feasible under these assumptions. A sensitivity study showed that, at P90, it would only break even at about 165% of the assumed electricity price, or at about 45% of the assumed construction cost.